Completion

NOTICE OF SUBSTANTIAL COMPLETION

AND

RETAINAGE RELEASE

In accordance with the provisions of paragraph 16-6-116, Wyoming State Statutes, 2020 Revised Edition, the Town Of Pine Haven, hereby gives notice that Simon Contractors, Inc, whose address is 209 N. Limestone Avenue, Gillette, WY 82717, as prime contractor, has reached substantial completion on the 2022 Double Chip Seal project in accordance with the specifications and rules set forth in the contract entered into by the Town of Pine Haven and Simon Contractors on the effective date of September 16, 2022.

With the Certificate of Substantial Completion issued on this project, the general contractor is entitled to payment upon the forty-first (41st) day after this notice was first published for the amount retained under W.S. 16-6-702(b) together with any other amount due under the contract, less any amount withheld for the portion of work that is incomplete or not completed.

Payment will be made on July 31, 2024, the forty-first (41st) day from publishing this acceptance. Any disputed claims for material and labor performed under the contract should be made to the Town of Pine Haven, 24 Waters Drive, Pine Haven, WY 82721 prior to this date.

Town of Pine Haven

Karla Brandenburg, Mayor

Publish: June 20 and 27, 2024