The Voice of the Community Since 1909, Serving Moorcroft and Pine Haven, Wyoming
Lagoon cell 2 liquid removal is near completion with sludge removal to follow next. This will continue for the next two weeks.
Additionally, RCS has removed the old equipment from the blower building and is currently preparing for the new aeration equipment. They plan to have aeration back online for lagoon cell 2 once the piping is installed after sludge removal has been completed.