The Voice of the Community Since 1909, Serving Moorcroft and Pine Haven, Wyoming
Sorted by date Results 1 - 1 of 1
Last week, the contractor, Wyoming Earthmoving Corporation (WEC) completed the prime coat and blotter sand installation portion for the entire project on: West Pine, East Pine Streets, Cottonwood Street, Cedar Street, Spruce Street and Cedar Hills Drive. They also completed the first application of chip sealing on West Pine, East Pine Streets and Cottonwood Street. WEC is scheduled to complete the first and second chip seal application this week, which completes the project....